Interreg VI-A Romania–Bulgaria is small, concrete and local: fifteen counties and districts along the Danube, projects of a few hundred thousand euros, partners who know each other. It is also the programme where first-time partners most often underestimate two things: the paperwork per euro and the time between spending and reimbursement. This page is for an organisation — Romanian, Bulgarian or from elsewhere joining as associated partner — entering the programme for the first time.
In brief
- Area: 7 Romanian counties (Mehedinți, Dolj, Olt, Teleorman, Giurgiu, Călărași, Constanța) and 8 Bulgarian districts (Vidin, Vratsa, Montana, Pleven, Veliko Tarnovo, Ruse, Silistra, Dobrich). Partners must be based in the area or, in limited cases, demonstrate benefit for it.
- Money: ERDF 80 %, national state budget 18 %, partner’s own contribution 2 % — on both sides of the border.
- Simplified costs: staff is a flat rate of up to 20 % of direct costs (external expertise and services, equipment, works); office and administration and travel are each 15 % of staff costs. You do not report salaries or timesheets — but you report every external invoice in detail.
- Verification: each partner’s expenditure is checked by a national controller before it can be claimed — in Romania by the Regional Office for Cross-Border Cooperation (BRCT) Călărași. Reports are quarterly; verification takes weeks, reimbursement from a few weeks to several months.
- Cash-flow: pre-financing is a single tranche of 75 % of the national co-financing (i.e. a fraction of the budget, not 75 % of it). Plan how you will finance the rest until reimbursement — this is the one thing we would tell every first-time partner.
- System: everything — application, contracting, reports, payment claims — goes through Jems, the joint electronic monitoring system.
1. Who can take part and in what role
| Role | Who | What it means |
|---|---|---|
| Lead partner | a public or private non-profit body from the programme area, from either country | signs the subsidy contract, receives ERDF for the whole partnership, transfers each partner’s share, is liable for recoveries |
| Project partner | public bodies, NGOs, universities, chambers, in some calls SMEs, from the area | own budget line, own national controller, own 2 % contribution |
| Associated partner | any organisation, inside or outside the area | no budget, no reimbursement (travel may be covered by a partner), useful for expertise and dissemination |
Every project must have at least one Romanian and one Bulgarian partner and meet at least three of the four cooperation criteria (joint development, joint implementation, joint staffing, joint financing). A single NGO cannot apply alone; the “partner search” period before each call is therefore real work, not a formality.
2. The budget: what you actually report
| Cost category | Rule | What the controller sees |
|---|---|---|
| Staff | flat rate, up to 20 % of direct costs (external expertise and services, equipment, infrastructure and works); preparation and closure costs excluded from the base | nothing — no contracts, payslips or timesheets |
| Office and administrative | flat rate, up to 15 % of staff costs | nothing |
| Travel and accommodation | flat rate, up to 15 % of staff costs (external experts’ travel on real costs) | nothing for staff travel |
| External expertise and services | real costs | procurement file, contract, invoice, proof of payment, deliverable |
| Equipment | real costs | procurement file, invoice, payment, inventory, photos |
| Infrastructure and works | real costs | full works documentation |
The consequence: a soft project (training, events, studies) is in practice a services project. Its eligibility and its cash-flow depend on how you contract trainers, venues and studies. Public procurement rules apply to NGOs too, under the national thresholds; a procurement file that fails control is the most common cause of financial corrections.
3. Verification, reporting and payment — the timeline
- Spend and document. Costs are incurred in lei or leva. They are reported in euro at the European Commission’s monthly accounting rate of the month in which the expenditure is submitted for verification; the exchange-rate difference stays with the partner.
- Request verification. Each partner submits its expenditure to its national controller through Jems. In Romania the controller is BRCT Călărași. Reporting periods are quarterly; in our experience a verification request can be submitted as soon as a meaningful amount of eligible expenditure has accumulated (around €10,000) — check the current Implementation Manual for the exact rule.
- Control. The controller checks documents and, for some items, on the spot. Expect a few weeks, longer if clarifications are requested.
- Progress report and payment claim. The lead partner compiles the verified expenditure of all partners into the project report and payment claim in Jems.
- Payment. ERDF is paid to the lead partner, who transfers each partner’s share; the national co-financing is paid by each state to its own partners. From progress report to money in the account we have seen 2–3 weeks and 6 months, in the same programme.
4. Cash-flow: the one lesson
Pre-financing is 75 % of the national co-financing — of the 18 % state-budget share — paid in one tranche. On a €200,000 partner budget that is roughly €27,000. Everything else is reimbursed after verification. A first-time partner must therefore answer, before signing, a simple question: how will we pay suppliers and the flat-rate staff share for six to nine months if the first reimbursement is late? The answers we have seen work: a credit line or overdraft dedicated to the project, staggered supplier contracts with payment on reimbursement where the supplier accepts it, a lead partner that transfers ERDF within days of receiving it, and a realistic activity calendar that does not front-load spending in the first quarter.
5. Working across the border
- Two controllers, one project. Romanian and Bulgarian partners are each verified by their own national body, on their own timeline. The lead partner’s report can only be submitted when the slowest partner is verified. Agree internal deadlines that are earlier than the programme’s.
- Language. Programme documents are in English; controllers work in Romanian and Bulgarian with their own partners. Keep one English version of every joint deliverable from day one.
- Joint events on the other side of the border: the hosting partner contracts and pays; the visiting partner’s costs are covered by its flat rates. Decide who pays what in the partnership agreement, event by event.
- Indicators (participants, organisations cooperating across borders, jointly developed solutions) are counted per project, not per partner — one list, one methodology, agreed at the start.
Frequently asked questions
Who is eligible as a partner in Interreg Romania–Bulgaria?
Public bodies, NGOs, universities, chambers and similar non-profit organisations based in the 7 Romanian counties and 8 Bulgarian districts along the border; each project needs at least one partner from each country. Organisations outside the area can join as associated partners without budget.
How are staff costs reimbursed?
As a flat rate of up to 20 % of direct costs (external expertise and services, equipment, works), without timesheets or payslips. Office and administrative costs and travel are each a flat rate of up to 15 % of staff costs.
Who verifies the expenditure of a Romanian partner, and how long does it take?
The Regional Office for Cross-Border Cooperation (BRCT) Călărași, through Jems. Verification typically takes a few weeks; reimbursement after the project report has ranged, in our experience, from two–three weeks to six months.
How much pre-financing does a partner receive?
One tranche of 75 % of the national co-financing (the 18 % state-budget share) — a small fraction of the budget. The rest is reimbursed after verification, so partners must secure their own cash-flow.
Does a Romanian NGO need public procurement for project purchases?
Yes. Private beneficiaries apply the procurement procedure set by the national rules for EU-funded projects, with thresholds and documentation defined in the Implementation Manual. Procurement files are the most frequent source of financial corrections.
Sources
- Interreg VI-A Romania–Bulgaria Programme, approved by the European Commission (2022); Applicant’s Guide — sections 2.5 (budget and co-financing: ERDF 80 %, state budget 18 %, own contribution 2 %), 2.9 (eligibility of expenditure and flat rates), 2.15 (submission through Jems); Project Implementation Manual and Implementation Rules (interregviarobg.eu) for verification, reporting and procurement.
- Regulation (EU) 2021/1059 (Interreg), including the rules on use of the euro and management verifications.
- Our implementation records as project partner since 2014, most recently INES (ROBG00226) with Active Society Association, Vidin.
General information, not legal or financial advice. Programme rules are set per call; the Implementation Manual in force at contracting prevails.
About this series
Written by Forever for Europe Association (AMPE), Craiova — partner in Interreg Romania–Bulgaria projects in three programming periods, and partner or lead partner in ESF+ and Europe Direct projects since 2005. Other parts: legal forms and eligibility · ANC authorisation and certificates · co-financing, pre-financing and cash-flow · VAT, invoicing and staff costs. Looking for a Romanian partner in Dolj for the next call: mpe@mpe.ro · Partner with us.